Section 6117.01 | Power to establish sewer districts - sanitary engineering department.
Effective:
October 16, 2009
Latest Legislation:
House Bill 1 - 128th General Assembly
(A) As used in this chapter: (1) "Sanitary facilities" means sanitary sewers, force mains, lift or pumping stations, and facilities for the treatment, disposal, impoundment, or storage of wastes; equipment and furnishings; and all required appurtenances and necessary real estate and interests in real estate. (2) "Drainage" or "waters" means flows from rainfall or otherwise produced by, or resulting from, the elements, storm water discharges and releases or migrations of waters from properties, accumulations, flows, and overflows of water, including accelerated flows and runoffs, flooding and threats of flooding of properties and structures, and other surface and subsurface drainage. (3) "Drainage facilities" means storm sewers, force mains, pumping stations, and facilities for the treatment, disposal, impoundment, retention, control, or storage of waters; improvements of or for any channel, ditch, drain, floodway, or watercourse, including location, construction, reconstruction, reconditioning, widening, deepening, cleaning, removal of obstructions, straightening, boxing, culverting, tiling, filling, walling, arching, or change in course, location, or terminus; improvements of or for a river, creek, or run, including reinforcement of banks, enclosing, deepening, widening, straightening, removal of obstructions, or change in course, location, or terminus; facilities for the protection of lands from the overflow of water, including a levee, wall, embankment, jetty, dike, dam, sluice, revetment, reservoir, retention or holding basin, control gate, or breakwater; facilities for controlled drainage, regulation of stream flow, and protection of an outlet; the vacation of a ditch or drain; equipment and furnishings; and all required appurtenances and necessary real estate and interests in real estate. (4) "County sanitary engineer" means either of the following: (a) The registered professional engineer employed or appointed by the board of county commissioners to be the county sanitary engineer as provided in this section3; (b) The county engineer, if, for as long as and to the extent that engineer by agreement entered into under section 315.14 of the Revised Code is retained to discharge duties of a county sanitary engineer under this chapter. (5) "Current operating expenses," "debt charges," "permanent improvement," "public obligations," and "subdivision" have the same meanings as in section 133.01 of the Revised Code. (6) "Construct," "construction," or "constructing" means construction, reconstruction, enlargement, extension, improvement, renovation, repair, and replacement of sanitary or drainage facilities or of prevention or replacement facilities, but does not include any repairs, replacements, or similar actions that do not constitute and qualify as permanent improvements. (7) "Maintain," "maintaining," or "maintenance" means repairs, replacements, and similar actions that constitute and are payable as current operating expenses and that are required to restore sanitary or drainage facilities or prevention or replacement facilities to, or to continue sanitary or drainage facilities or prevention or replacement facilities in, good order and working condition, but does not include construction of permanent improvements. (8) "Public agency" means a state and any agency or subdivision of a state, including a county, a municipal corporation, or other subdivision. (9) "Combined sewer" means a sewer system that is designed to collect and convey sewage, including domestic, commercial, and industrial wastewater, and storm water through a single-pipe system to a treatment works or combined sewer overflow outfall approved by the director of environmental protection. (10) "Prevention or replacement facilities" means vegetated swales or median strips, permeable pavement, trees and tree boxes, rain barrels and cisterns, rain gardens and filtration planters, vegetated roofs, wetlands, riparian buffers, and practices and structures that use or mimic natural processes to filter or reuse storm water. (11) "Homestead exemption" means the reduction of taxes allowed under division (A) of section 323.152 of the Revised Code. (12) "Low- and moderate-income person" has the same meaning as in section 175.01 of the Revised Code. (B)(1) For the purpose of preserving and promoting the public health and welfare, a board of county commissioners may lay out, establish, consolidate, or otherwise modify the boundaries of, and maintain, one or more sewer districts within the county and outside municipal corporations and may have a registered professional engineer make the surveys necessary for the determination of the proper boundaries of each district, which shall be designated by an appropriate name or number. The board may acquire, construct, maintain, and operate within any district sanitary or drainage facilities that it determines to be necessary or appropriate for the collection of sewage and other wastes originating in or entering the district, to comply with the provisions of a contract entered into for the purposes described in sections 6117.41 to 6117.44 of the Revised Code and pursuant to those sections or other applicable provisions of law, or for the collection, control, or abatement of waters originating or accumulating in, or flowing in, into, or through, the district, and other sanitary or drainage facilities, within or outside of the district, that it determines to be necessary or appropriate to conduct the wastes and waters to a proper outlet and to provide for their proper treatment, disposal, and disposition. The board may provide for the protection of the sanitary and drainage facilities and may negotiate and enter into a contract with any public agency or person for the management, maintenance, operation, and repair of any of the facilities on behalf of the county upon the terms and conditions that may be agreed upon with the agency or person and that may be determined by the board to be in the best interests of the county. By contract with any public agency or person operating sanitary or drainage facilities within or outside of the county, the board may provide a proper outlet for any of the wastes and waters and for their proper treatment, disposal, and disposition. (2) For purposes of preventing storm water from entering a combined sewer and causing an overflow or an inflow to a sanitary sewer, the board may acquire, design, construct, operate, repair, maintain, and provide for a project or program that separates storm water from a combined sewer or for a prevention or replacement facility that prevents or minimizes storm water from entering a combined sewer or a sanitary sewer. (C) The board of county commissioners may employ a registered professional engineer to be the county sanitary engineer for the time and on the terms it considers best and may authorize the county sanitary engineer to employ necessary assistants upon the terms fixed by the board. Prior to the initial assignment of drainage facilities duties to the county sanitary engineer, if the county sanitary engineer is not the county engineer, the board first shall offer to enter into an agreement with the county engineer pursuant to section 315.14 of the Revised Code for assistance in the performance of those duties of the board pertaining to drainage facilities, and the county engineer shall accept or reject the offer within thirty days after the date the offer is made. The board may create and maintain a sanitary engineering department, which shall be under its supervision and which shall be headed by the county sanitary engineer, for the purpose of aiding it in the performance of its duties under this chapter and Chapter 6103. of the Revised Code or its other duties regarding sanitation, drainage, and water supply provided by law. The board shall provide suitable facilities for the use of the department and shall provide for and pay the compensation of the county sanitary engineer and all authorized necessary expenses of the county sanitary engineer and the sanitary engineering department. The county sanitary engineer, with the approval of the board, may appoint necessary assistants and clerks, and the compensation of those assistants and clerks shall be provided for and paid by the board. (D) The board of county commissioners may adopt, publish, administer, and enforce rules for the construction, maintenance, protection, and use of county-owned or county-operated sanitary and drainage facilities and prevention or replacement facilities outside municipal corporations, and of sanitary and drainage facilities and prevention or replacement facilities within municipal corporations that are owned or operated by the county or that discharge into sanitary or drainage facilities or prevention or replacement facilities owned or operated by the county, including, but not limited to, rules for the establishment and use of any connections, the termination in accordance with reasonable procedures of sanitary service for the nonpayment of county sanitary rates and charges and, if so determined, the concurrent termination of any county water service for the nonpayment of those rates and charges, the termination in accordance with reasonable procedures of drainage service for the nonpayment of county drainage rates and charges, and the establishment and use of security deposits to the extent considered necessary to ensure the payment of county sanitary or drainage rates and charges. The rules shall not be inconsistent with the laws of this state or any applicable rules of the director of environmental protection. (E) No sanitary or drainage facilities or prevention or replacement facilities shall be constructed in any county outside municipal corporations by any person until the plans and specifications have been approved by the board of county commissioners, and any construction shall be done under the supervision of the county sanitary engineer. Not less than thirty days before the date drainage plans are submitted to the board for its approval, the plans shall be submitted to the county engineer. If the county engineer is of the opinion after review that the facilities will have a significant adverse effect on roads, culverts, bridges, or existing maintenance within the county, the county engineer may submit a written opinion to the board not later than thirty days after the date the plans are submitted to the county engineer. The board may take action relative to the drainage plans only after the earliest of receiving the written opinion of the county engineer, receiving a written waiver of submission of an opinion from the county engineer, or passage of thirty days from the date the plans are submitted to the county engineer. Any person constructing the facilities shall pay to the county all expenses incurred by the board in connection with the construction. (F) The county sanitary engineer or the county sanitary engineer's authorized assistants or agents, when properly identified in writing or otherwise and after written notice is delivered to the owner at least five days in advance or is mailed at least five days in advance by first class or certified mail to the owner's tax mailing address, may enter upon any public or private property for the purpose of making, and may make, surveys or inspections necessary for the laying out of sewer districts or the design or evaluation of county sanitary or drainage facilities or prevention or replacement facilities. This entry is not a trespass and is not to be considered an entry in connection with any appropriation of property proceedings under sections 163.01 to 163.22 of the Revised Code that may be pending. No person or public agency shall forbid the county sanitary engineer or the county sanitary engineer's authorized assistants or agents to enter, or interfere with their entry, upon the property for that purpose or forbid or interfere with their making of surveys or inspections. If actual damage is done to property by the making of the surveys and inspections, the board shall pay the reasonable value of the damage to the property owner, and the cost shall be included in the cost of the facilities and may be included in any special assessments to be levied and collected to pay that cost.
|
Section 6117.011 | Surveys of water supply, sanitary, or drainage facilities.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
A board of county commissioners in the manner provided in this section may make surveys of water supply, sanitary facilities, drainage facilities, or prevention or replacement facilities for any sewer district, the acquisition or construction of which is contemplated. Any board desiring to make a survey shall adopt a resolution declaring its purpose and necessity. In making the surveys, the board may call upon engineering officers or employees regularly employed by the board or may authorize and enter into contracts for the services of registered professional engineers to make the surveys. The surveys authorized by this section may include drawings, plans, specifications, estimates of cost of labor and materials, other items of cost, assessment rolls, and other facts, material, data, reports, and information and recommendations that the board considers advisable or necessary for the purpose. Contracts entered into for the surveys shall be considered contracts for professional services and may provide for preliminary surveys or the making of detailed plans, or both, and also may provide for engineering supervision of the work. No contract shall be valid unless one or more of the services to be performed are by its terms to be commenced within one year after the contract date. The contracts shall be signed by at least two members of the board and by the engineer agreeing to perform the service, and one signed copy of the contract shall be filed with the fiscal officer of the county, whose certificate, otherwise required by section 5705.41 of the Revised Code, need not be provided. Payment for the contracts may be made from the general fund or any other fund legally available for that use at the times that are agreed upon or as determined by the board. The proceeds of any public obligations issued pursuant to section 6119.36 of the Revised Code or any other public obligations issued or incurred to pay the cost of facilities to which a survey relates may be used to pay any part of the cost under the contracts or to reimburse the fund from which payment was made.
|
Section 6117.012 | Rules for disconnection and reconnection or relocation of improper inflows into sewers.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
(A) A board of county commissioners may adopt rules requiring owners of property within the district whose property is served by a connection to sewers maintained and operated by the board or to sewers that are connected to interceptor sewers maintained and operated by the board to do any of the following: (1) Disconnect storm water inflows to sanitary sewers maintained and operated by the board and not operated as a combined sewer, or to connections with those sewers; (2) Disconnect non-storm water inflows to storm water sewers maintained and operated by the board and not operated as a combined sewer, or to connections with those storm water sewers; (3) Reconnect or relocate any such disconnected inflows in compliance with board rules and applicable building codes, health codes, or other relevant codes; (4) Prevent sewer back-ups into properties that have experienced one or more back-ups of sanitary or combined sewers maintained and operated by the board; (5) Prevent storm water from entering a combined sewer and causing an overflow or an inflow to a sanitary sewer, which prevention may include projects or programs that separate the storm water from a combined sewer or that utilize a prevention or replacement facility to prevent or minimize storm water from entering a combined sewer or a sanitary sewer. (B) Any inflow required to be disconnected or any sewer back-up required to be prevented under a rule adopted pursuant to divisions (A)(1) to (4) of this section constitutes a nuisance subject to injunctive relief and abatement pursuant to Chapter 3767. of the Revised Code or as otherwise permitted by law. (C) A board of county commissioners may use sewer district funds; county general fund moneys; the proceeds of bonds issued under Chapter 133. or 165. of the Revised Code; and, to the extent permitted by their terms, loans, grants, or other moneys from appropriate state or federal funds, for either of the following: (1) The cost of disconnections, reconnections, relocations, combined sewer overflow prevention, or sewer back-up prevention required by rules adopted pursuant to division (A) of this section, performed by the county or under contract with the county; (2) Payments to the property owner or a contractor hired by the property owner pursuant to a competitive process established by district rules, for the cost of disconnections, reconnections, relocations, combined sewer overflow prevention, or sewer back-up prevention required by rules adopted pursuant to division (A) of this section after the board, pursuant to its rules, has approved the work to be performed and after the county has received from the property owner a statement releasing the county from all liability in connection with the disconnections, reconnections, relocations, combined sewer overflow prevention, or sewer back-up prevention. (D) Except as provided in division (E) of this section, the board of county commissioners shall require in its rules regarding disconnections, reconnections, relocations of sewers, combined sewer overflow prevention, or sewer back-up prevention the reimbursement of moneys expended pursuant to division (C) of this section by either of the following methods: (1) A charge to the property owner in the amount of the payment made pursuant to division (C) of this section for immediate payment or payment in installments with interest as determined by the board not to exceed ten per cent, which payments may be billed as a separate item with the rents charged to that owner for use of the sewers. The board may approve installment payments for a period of not more than fifteen years. If charges are to be paid in installments, the board shall certify to the county auditor information sufficient to identify each subject parcel of property, the total of the charges to be paid in installments, and the total number of installments to be paid. The auditor shall record the information in the sewer improvement record until these charges are paid in full. Charges not paid when due shall be certified to the county auditor, who shall place the charges upon the real property tax list and duplicate against that property. Those charges shall be a lien on the property from the date they are placed on the tax list and duplicate and shall be collected in the same manner as other taxes. (2) A special assessment levied against the property, payable in the number of years the board determines, not to exceed fifteen years, with interest as determined by the board not to exceed ten per cent. The board shall certify the assessments to the county auditor, stating the amount and time of payment. The auditor shall record the information in the county sewer improvement record, showing separately the assessments to be collected, and shall place the assessments upon the real property tax list and duplicate for collection. The assessments shall be a lien on the property from the date they are placed on the tax list and duplicate and shall be collected in the same manner as other taxes. (E) The county may adopt a resolution specifying a maximum amount of the cost of any disconnection, reconnection, relocation, combined sewer overflow prevention, or sewer back-up prevention required pursuant to division (A) of this section that may be paid by the county for each affected parcel of property without requiring reimbursement. That amount may be allowed only if there is a building code, health code, or other relevant code, or a federally imposed or state-imposed consent decree that is filed or otherwise recorded in a court of competent jurisdiction, applicable to the affected parcel that prohibits in the future any inflows, combined sewer overflows, or sewer back-ups not allowed under rules adopted pursuant to division (A)(1), (4), or (5) of this section. The board, by rule, shall establish criteria for determining how much of the maximum amount for each qualifying parcel need not be reimbursed. (F) Disconnections, reconnections, relocations, combined sewer overflow prevention, or sewer back-up prevention required under this section and performed by a contractor under contract with the property owner shall not be considered a public improvement, and those performed by the county shall be considered a public improvement as defined in section 4115.03 of the Revised Code. Disconnections, reconnections, relocations, combined sewer overflow prevention, or sewer back-up prevention required under this section performed by a contractor under contract with the property owner shall not be subject to competitive bidding or public bond laws. (G) Property owners shall be responsible for maintaining any improvements made or facilities constructed on private property to reconnect or relocate disconnected inflows, for combined sewer overflow prevention, or for sewer back-up prevention pursuant to this section unless a public easement or other agreement exists for the county to maintain that improvement or facility. (H) A board of county commissioners may provide rate reductions of and credits against charges for the use of sewers to a property owner that implements a project or program that prevents storm water from entering a combined sewer and causing an overflow. Such a project or program may include the use of a prevention or replacement facility to handle storm water that has been separated from a combined sewer. The revised rates or charges shall be collected and paid to the county treasurer in accordance with section 6117.02 of the Revised Code.
|
Section 6117.02 | Sanitary rates, charges, or penalties fixed or established.
Effective:
October 16, 2009
Latest Legislation:
House Bill 1 - 128th General Assembly
(A) The board of county commissioners shall fix reasonable rates, including penalties for late payments, for the use, or the availability for use, of the sanitary facilities of a sewer district to be paid by every person and public agency whose premises are served, or capable of being served, by a connection directly or indirectly to those facilities when those facilities are owned or operated by the county and may change the rates from time to time as it considers advisable. When the sanitary facilities to be used by the county are owned by another public agency or person, the schedule of rates to be charged by the public agency or person for the use of the facilities by the county, or the formula or other procedure for their determination, shall be approved by the board at the time it enters into a contract for that use. (B) The board also shall establish reasonable charges to be collected for the privilege of connecting to the sanitary facilities of the district, with the requirement that, prior to the connection, the charges shall be paid in full, or, if determined by the board to be equitable in a resolution relating to the payment of the charges, provision considered adequate by the board shall be made for their payment in installments at the times, in the amounts, and with the security, carrying charges, and penalties as may be found by the board in that resolution to be fair and appropriate. No public agency or person shall be permitted to connect to those facilities until the charges have been paid in full or provision for their payment in installments has been made. If the connection charges are to be paid in installments, the board shall certify to the county auditor information sufficient to identify each parcel of property served by a connection and, with respect to each parcel, the total of the charges to be paid in installments, the amount of each installment, and the total number of installments to be paid. The auditor shall record and maintain the information supplied in the sewer improvement record provided for in section 6117.33 of the Revised Code until the connection charges are paid in full. The board may include amounts attributable to connection charges being paid in installments in its billings of rates and charges for the use of sanitary facilities. (C) When any of the sanitary rates or charges are not paid when due, the board may do any or all of the following as it considers appropriate: (1) Certify the unpaid rates or charges, together with any penalties, to the county auditor, who shall place them upon the real property tax list and duplicate against the property served by the connection. The certified amount shall be a lien on the property from the date placed on the real property tax list and duplicate and shall be collected in the same manner as taxes, except that, notwithstanding section 323.15 of the Revised Code, a county treasurer shall accept a payment in that amount when separately tendered as payment for the full amount of the unpaid sanitary rates or charges and associated penalties. The lien shall be released immediately upon payment in full of the certified amount. (2) Collect the unpaid rates or charges, together with any penalties, by actions at law in the name of the county from an owner, tenant, or other person or public agency that is liable for the payment of the rates or charges; (3) Terminate, in accordance with established rules, the sanitary service to the particular property and, if so determined, any county water service to that property, unless and until the unpaid sanitary rates or charges, together with any penalties, are paid in full; (4) Apply, to the extent required, any security deposit made in accordance with established rules to the payment of sanitary rates and charges for service to the particular property. All moneys collected as sanitary rates, charges, or penalties fixed or established in accordance with divisions (A) and (B) of this section for any sewer district shall be paid to the county treasurer and kept in a separate and distinct sanitary fund established by the board to the credit of the district. Except as otherwise provided in any proceedings authorizing or providing for the security for and payment of any public obligations, or in any indenture or trust or other agreement securing public obligations, moneys in the sanitary fund shall be applied first to the payment of the cost of the management, maintenance, and operation of the sanitary facilities of, or used or operated for, the district, which cost may include the county's share of management, maintenance, and operation costs under cooperative contracts for the acquisition, construction, or use of sanitary facilities and, in accordance with a cost allocation plan adopted under division (E) of this section, payment of all allowable direct and indirect costs of the district, the county sanitary engineer or sanitary engineering department, or a federal or state grant program, incurred for sanitary purposes under this chapter, and shall be applied second to the payment of debt charges payable on any outstanding public obligations issued or incurred for the acquisition or construction of sanitary facilities for or serving the district, or for the funding of a bond retirement or other fund established for the payment of or security for the obligations. Any surplus remaining may be applied to the acquisition or construction of those facilities or for the payment of contributions to be made, or costs incurred, for the acquisition or construction of those facilities under cooperative contracts. Moneys in the sanitary fund shall not be expended other than for the use and benefit of the district. (D) The board may fix reasonable rates and charges, including connection charges and penalties for late payments, to be paid by any person or public agency owning or having possession or control of any properties that are connected with, capable of being served by, or otherwise served directly or indirectly by, drainage facilities owned or operated by or under the jurisdiction of the county, including, but not limited to, properties requiring, or lying within an area of the district requiring, in the judgment of the board, the collection, control, or abatement of waters originating or accumulating in, or flowing in, into, or through, the district, and may change those rates and charges from time to time as it considers advisable. In addition, the board may fix the rates and charges in order to pay the costs of complying with the requirements of phase II of the storm water program of the national pollutant discharge elimination system established in 40 C.F.R. part 122. The rates and charges shall be payable periodically as determined by the board, except that any connection charges shall be paid in full in one payment, or, if determined by the board to be equitable in a resolution relating to the payment of those charges, provision considered adequate by the board shall be made for their payment in installments at the times, in the amounts, and with the security, carrying charges, and penalties as may be found by the board in that resolution to be fair and appropriate. The board may include amounts attributable to connection charges being paid in installments in its billings of rates and charges for the services provided by the drainage facilities. In the case of rates and charges that are fixed in order to pay the costs of complying with the requirements of phase II of the storm water program of the national pollutant discharge elimination system established in 40 C.F.R. part 122, the rates and charges may be paid annually or semiannually with real property taxes, provided that the board certifies to the county auditor information that is sufficient for the auditor to identify each parcel of property for which a rate or charge is levied and the amount of the rate or charge. When any of the drainage rates or charges are not paid when due, the board may do any or all of the following as it considers appropriate: (1) Certify the unpaid rates or charges, together with any penalties, to the county auditor, who shall place them upon the real property tax list and duplicate against the property to which the rates or charges apply. The certified amount shall be a lien on the property from the date placed on the real property tax list and duplicate and shall be collected in the same manner as taxes, except that notwithstanding section 323.15 of the Revised Code, a county treasurer shall accept a payment in that amount when separately tendered as payment for the full amount of the unpaid drainage rates or charges and associated penalties. The lien shall be released immediately upon payment in full of the certified amount. (2) Collect the unpaid rates or charges, together with any penalties, by actions at law in the name of the county from an owner, tenant, or other person or public agency that is liable for the payment of the rates or charges; (3) Terminate, in accordance with established rules, the drainage service for the particular property until the unpaid rates or charges, together with any penalties, are paid in full; (4) Apply, to the extent required, any security deposit made in accordance with established rules to the payment of drainage rates and charges applicable to the particular property. All moneys collected as drainage rates, charges, or penalties in or for any sewer district shall be paid to the county treasurer and kept in a separate and distinct drainage fund established by the board to the credit of the district. Except as otherwise provided in any proceedings authorizing or providing for the security for and payment of any public obligations, or in any indenture or trust or other agreement securing public obligations, moneys in the drainage fund shall be applied first to the payment of the cost of the management, maintenance, and operation of the drainage facilities of, or used or operated for, the district, which cost may include the county's share of management, maintenance, and operation costs under cooperative contracts for the acquisition, construction, or use of drainage facilities and, in accordance with a cost allocation plan adopted under division (E) of this section, payment of all allowable direct and indirect costs of the district, the county sanitary engineer or sanitary engineering department, or a federal or state grant program, incurred for drainage purposes under this chapter, and shall be applied second to the payment of debt charges payable on any outstanding public obligations issued or incurred for the acquisition or construction of drainage facilities for or serving the district, or for the funding of a bond retirement or other fund established for the payment of or security for the obligations. Any surplus remaining may be applied to the acquisition or construction of those facilities or for the payment of contributions to be made, or costs incurred, for the acquisition or construction of those facilities under cooperative contracts. Moneys in the drainage fund shall not be expended other than for the use and benefit of the district. (E) A board of county commissioners may adopt a cost allocation plan that identifies, accumulates, and distributes allowable direct and indirect costs that may be paid from each of the funds of the district created pursuant to divisions (C) and (D) of this section, and that prescribes methods for allocating those costs. The plan shall authorize payment from each of those funds of only those costs incurred by the district, the county sanitary engineer or sanitary engineering department, or a federal or state grant program, and those costs incurred by the general and other funds of the county for a common or joint purpose, that are necessary and reasonable for the proper and efficient administration of the district under this chapter and properly attributable to the particular fund of the district. The plan shall not authorize payment from either of the funds of any general government expense required to carry out the overall governmental responsibilities of a county. The plan shall conform to United States office of management and budget Circular A-87, "Cost Principles for State, Local, and Indian Tribal Governments," published May 17, 1995. (F) A board of county commissioners may establish discounted rates or charges or may establish another mechanism for providing a reduction in rates or charges for persons who are sixty-five years of age or older. The board shall establish eligibility requirements for such discounted or reduced rates or charges, including a requirement that a person be eligible for the homestead exemption or qualify as a low- and moderate-income person.
Last updated February 14, 2022 at 12:13 PM
|
Section 6117.021 | Contracts for purpose of complying with phase II of storm water program.
Effective:
September 29, 2015
Latest Legislation:
House Bill 64 - 131st General Assembly
At any time after the formation of a county sewer district, the board of county commissioners may enter into a contract, on terms and for the period of time that are mutually agreed on, with any other public agency under which the public agency will conduct projects and activities for the purpose of complying with the requirements of phase II of the storm water program of the national pollutant discharge elimination system established in 40 C.F.R. part 122.
|
Section 6117.03 | Resolution to lay out, establish, and maintain one or more sewer districts within county.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
Whenever authorized by the legislative authority of any municipal corporation, the board of county commissioners may by resolution lay out, establish, and maintain one or more sewer districts within its county to include a part or all of the territory within such municipal corporation as the whole or a part of such district. Such authority shall be evidenced by an ordinance or resolution of the legislative authority of such municipal corporation, entered upon its records.
|
Section 6117.04 | Authority of board of county commissioners to acquire, construct, maintain, and operate sanitary or drainage facilities.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
The authority of a board of county commissioners to acquire, construct, maintain, and operate sanitary or drainage facilities or prevention or replacement facilities for a county sewer district in the territory of a municipal corporation, or a regional district established under Chapter 6119. of the Revised Code, that is in whole or in part within the county sewer district is the same as provided by law with respect to territory within a county sewer district that is wholly outside a municipal corporation or a regional district, subject to the following in the case of facilities within a municipal corporation: (A) The acquisition, construction, maintenance, and operation of the facilities shall first be authorized by an ordinance or resolution of the legislative authority of the municipal corporation. (B) All road surfaces, curbs, sidewalks, sewers, water supply facilities, or other public improvements or property that may be disturbed or damaged by the construction of the facilities shall be replaced or restored within a reasonable time by the county, and the cost shall be treated as a part of the cost of the facilities. (C) The municipal corporation, with the prior approval of or by agreement with the board, may make use of the facilities in accordance with rules established by the board and subject to any applicable requirements of the director of environmental protection.
|
Section 6117.05 | Continuing jurisdiction where area is incorporated into or annexed to municipal corporation.
Effective:
September 29, 2011
Latest Legislation:
House Bill 153 - 129th General Assembly
(A) Whenever any portion of a sewer district is incorporated as, or annexed to, a municipal corporation, the area so incorporated or annexed shall remain under the jurisdiction of the board of county commissioners for purposes of the acquisition and construction of sanitary and drainage facility and prevention or replacement facility improvements until all of those improvements for the area for which a resolution described in division (A) or (E) of section 6117.06 of the Revised Code has been adopted by the board have been acquired or completed or until the board has abandoned the improvements. The board, unless and until a conveyance is made to a municipal corporation in accordance with division (B) of this section, shall continue to have jurisdiction in the area so incorporated or annexed with respect to the management, maintenance, and operation of all sanitary and drainage facilities and prevention or replacement facilities so acquired or completed, or previously acquired or completed, including the right to establish rules and rates and charges for the use of, and connections to, the facilities. The incorporation or annexation of any part of a district shall not affect the legality or enforceability of any public obligations issued or incurred by the county for purposes of this chapter to provide for the payment of the cost of acquisition, construction, maintenance, or operation of any sanitary or drainage facilities or prevention or replacement facilities within the area, or the validity of any assessments levied or to be levied upon properties within the area to provide for the payment of the cost of acquisition, construction, maintenance, or operation of the facilities. (B) A board may convey, by mutual agreement, to a municipal corporation any completed sanitary or drainage facilities or prevention or replacement facilities acquired or constructed by a county under this chapter for the use of, or service of property located in, any county sewer district, or any part of those facilities to which any of the following applies: (1) The facilities are located within the municipal corporation or within any area that is incorporated as, or annexed to, the municipal corporation. (2) The facilities serve the municipal corporation or any area that is located within or that is incorporated as, or annexed to, the municipal corporation. (3) The facilities are connected to facilities of the municipal corporation. The conveyance shall be completed with terms and for consideration as may be negotiated. Upon and after the conveyance, the municipal corporation shall manage, maintain, and operate the facilities in accordance with the agreement. The board may retain the right to joint use of all or part of any facilities so conveyed for the benefit of the district. Neither the validity of any assessment levied or to be levied, nor the legality or enforceability of any public obligations issued or incurred, to provide for the payment of the cost of the acquisition, construction, maintenance, or operation of the facilities or any part of them, shall be affected by the conveyance.
|
Section 6117.06 | General plan of sewerage or drainage.
Effective:
September 29, 2011
Latest Legislation:
House Bill 153 - 129th General Assembly
(A) After the establishment of any sewer district, the board of county commissioners, if a sanitary or drainage facility or prevention or replacement facility improvement is to be undertaken, may have the county sanitary engineer prepare, or otherwise cause to be prepared, for the district, or revise as needed, a general plan of sewerage or drainage that is as complete in each case as can be developed at the time and that is devised with regard to any existing sanitary or drainage facilities or prevention or replacement facilities in the district and present as well as prospective needs for additional sanitary or drainage facilities or prevention or replacement facilities in the district. After the general plan, in original or revised form, has been approved by the board, it may adopt a resolution generally describing the improvement that is necessary to be acquired or constructed in accordance with the particular plan, declaring that the improvement is necessary for the preservation and promotion of the public health and welfare, and determining whether or not special assessments are to be levied and collected to pay any part of the cost of the improvement. (B) If special assessments are not to be levied and collected to pay any part of the cost of the improvement, the board, in the resolution provided for in division (A) of this section or in a subsequent resolution, including a resolution authorizing the issuance or incurrence of public obligations for the improvement, may authorize the improvement and the expenditure of the funds required for its acquisition or construction and may proceed with the improvement without regard to the procedures otherwise required by divisions (C), (D), and (E) of this section and by sections 6117.07 to 6117.24 of the Revised Code. Those procedures are required only for improvements for which special assessments are to be levied and collected. (C) If special assessments are to be levied and collected pursuant to a determination made in the resolution provided for in division (A) of this section or in a subsequent resolution, the procedures referred to in division (B) of this section as being required for that purpose shall apply, and the board may have the county sanitary engineer prepare, or otherwise cause to be prepared, detailed plans, specifications, and an estimate of cost for the improvement, together with a tentative assessment of the cost based on the estimate. The tentative assessment shall be for the information of property owners and shall not be levied or certified to the county auditor for collection. The detailed plans, specifications, estimate of cost, and tentative assessment, if approved by the board, shall be carefully preserved in the office of the board or the county sanitary engineer and shall be open to the inspection of all persons interested in the improvement. (D) After the board's approval of the detailed plans, specifications, estimate of cost, and tentative assessment, and at least twenty-four days before adopting a resolution pursuant to division (E) of this section, the board, except to the extent that appropriate waivers of notice are obtained from affected owners, shall cause to be sent a notice of its intent to adopt the resolution to each owner of property proposed to be assessed that is listed on the records of the county auditor for current agricultural use value taxation pursuant to section 5713.31 of the Revised Code and that is not located in an agricultural district established under section 929.02 of the Revised Code. The notice shall satisfy all of the following: (1) Be sent by first class or certified mail; (2) Specify the proposed date of the adoption of the resolution; (3) Contain a statement that the improvement will be financed in whole or in part by special assessments and that all properties not located in an agricultural district established pursuant to section 929.02 of the Revised Code may be subject to a special assessment; (4) Contain a statement that an agricultural district may be established by filing an application with the county auditor. If it appears, by the return of the mailed notices or by other means, that one or more of the affected owners cannot be found or are not served by the mailed notice, the board shall cause the notice to be published once in a newspaper of general circulation in the county not later than ten days before the adoption of the resolution. (E) After complying with divisions (A), (C), and (D) of this section, the board may adopt a resolution declaring that the improvement, which shall be described as to its nature and its location, route, and termini, is necessary for the preservation and promotion of the public health and welfare, referring to the plans, specifications, estimate of cost, and tentative assessment, stating the place where they are on file and may be examined, and providing that the entire cost or a lesser designated part of the cost will be specially assessed against the benefited properties within the district and that any balance will be paid by the county at large from other available funds. The resolution also shall contain a description of the boundaries of that part of the district to be assessed and shall designate a time and place for objections to the improvement, to the tentative assessment, or to the boundaries of the assessment district to be heard by the board. The date of that hearing shall be not less than twenty-four days after the date of the first publication of the notice of the hearing required by this division. The board shall cause a notice of the hearing to be published once a week for two consecutive weeks in a newspaper of general circulation in the county or as provided in section 7.16 of the Revised Code. On or before the date of the second publication, the board shall cause to be sent by first class or certified mail a copy of the notice to every owner of property to be assessed for the improvement whose address is known. The notice shall set forth the time and place of the hearing, a summary description of the proposed improvement, including its general route and termini, a summary description of the area constituting the assessment district, and the place where the plans, specifications, estimate of cost, and tentative assessment are on file and may be examined. Each mailed notice also shall include a statement that the property of the addressee will be assessed for the improvement. The notice also shall be sent by first class or certified mail, on or before the date of the second publication, to the clerk, or to the official discharging the duties of a clerk, of any municipal corporation any part of which lies within the assessment district and shall state whether or not any property belonging to the municipal corporation is to be assessed and, if so, shall identify that property. At the hearing, or at any adjournment of the hearing, of which no further published or mailed notice need be given, the board shall hear all parties whose properties are proposed to be assessed. Written objections to or endorsements of the proposed improvement, its character and termini, the boundaries of the assessment district, or the tentative assessment shall be received by the board for a period of five days after the completion of the hearing, and no action shall be taken by the board in the matter until after that period has elapsed. The minutes of the hearing shall be entered on the journal of the board, showing the persons who appear in person or by attorney, and all written objections shall be preserved and filed in the office of the board.
|
Section 6117.061 | Deferment of collection of assessment.
Effective:
October 24, 1961
Latest Legislation:
House Bill 851 - 104th General Assembly
At any time prior to the expiration of the five-day period provided by section 6117.06 of the Revised Code for the filing of written objections, any owner of property to be assessed for an improvement under sections 6117.01 to 6117.45, inclusive, of the Revised Code may file with the board of county commissioners a request in writing for deferment of the collection of his assessment. Such request shall identify the property in connection with which the request for deferment is made, shall describe its present use, shall state its estimated market value, showing separately the value of the land and the value of the buildings thereon, shall state the reasons why a portion of the assessment should be deferred, and the amount to be deferred. The board shall promptly consider such request and, if it finds that it will be inequitable to certify the entire amount of such assessment upon completion of the improvement to the county auditor for collection, the board may order that the collection of a portion of such assessment, not exceeding seventy-five per cent thereof, shall be deferred as provided in section 6117.33 of the Revised Code. In determining whether it is inequitable to certify an assessment for immediate collection upon completion of the improvement, the board shall consider as significant the following factors: whether or not the property is presently unimproved; whether or not it is being used for farming or agricultural purposes; the extent to which it is in immediate need of sewer service; whether the tentative assessment is a disproportionately high percentage of the estimated market value of the property after the improvement will have been completed. All requests for the deferment of the collection of assessments shall be considered by the board before it adopts the improvement resolution provided for by section 6117.07 of the Revised Code, and, if the board orders any part of any assessment to be deferred for collection, the sanitary engineer shall forthwith revise the list of tentative assessments to accord with the order of the board thereby showing the amount of each assessment to be collected upon the completion of the improvement and the amount of each assessment to be deferred for collection. The decision of the board on any request for deferment shall be final and no appeal therefrom may be taken. The board may, for good cause shown and notwithstanding the failure of a property owner to file such request within the period provided in this section, consider a request for the deferment of an assessment at any time prior to the adoption of the resolution confirming the revised assessment provided for by section 6117.32 of the Revised Code.
|
Section 6117.062 | Deferment of collection of assessments for certain lines providing sewer facilities to industrial or residential developments.
Effective:
September 28, 2012
Latest Legislation:
Senate Bill 314 - 129th General Assembly
(A) At any time prior to the expiration of the five-day period provided by section 6117.06 of the Revised Code for the filing of written objections, any owner of property which is classified on the general tax list of the county auditor as agricultural land and has been assessed for the extension of a trunk sewer line over or along such property under sections 6117.01 to 6117.45 of the Revised Code may file with the board of county commissioners a request in writing for deferment of the collection of the assessment if the trunk sewer line provides sewer facilities to aid in the establishment of new industrial plants, the expansion of existing industrial plants, or such other industrial development, or provides sewer facilities to aid in the establishment of commercial and residential developments. Such request shall identify the property in connection with which the request for deferment is made, shall describe its present use and present classification on the general tax list of the county auditor, shall state its estimated market value, showing separately the value of the land and the value of the buildings thereon, shall state the reasons, if any, why a portion of the benefit of the improvement will not be realized until the use of the land is changed, and shall state the amount to be deferred. The board shall promptly consider such request and may order the deferment of the collection of that portion of the assessment representing a benefit from the improvement which will not be realized until the use of the land is changed. The board may, upon request of an owner whose property has been assessed for the extension of a trunk sewer line over or along such property under sections 6117.01 to 6117.45 of the Revised Code, defer all or any part of the assessment on property which is classified on the general tax list as agricultural land, by attributing the amount of such assessment or part thereof as tap-in charges, if the trunk sewer line provides sewer facilities to aid in the establishment of new industrial plants, the expansion of existing industrial plants, or such other industrial development, or provides sewer facilities to aid in the establishment of commercial and residential developments. Upon determination and approval of final assessments, the board of county commissioners shall certify all deferred assessments and a fee equal to two per cent of the amount of the deferred assessments to the county auditor. For purposes of this section, "assessment," "deferred assessment," or "assessment deferred under this section" mean the fee and the deferred assessment certified to the county auditor. The county auditor shall record an assessment deferred under this section in the sewer improvement record. Such record shall be kept until such time as the assessments are paid in full or certified for collection in installments as provided in this section. During the time when the assessment is deferred there shall be a lien on the property assessed, which lien shall arise at the time of recordation by the county auditor and which shall be in force until the assessments are paid in full or certified for collection in installments. (B) The board of county commissioners shall defer the collection of an assessment, except the amount of such assessment or part thereof attributable as tap-in charges, which has been deferred pursuant to division (A) of this section on or before January 1, 1987, beyond the expiration of the maximum time for the original deferment if the property owner requests in writing, no later than six months prior to the expiration of the original deferment, that the assessment be further deferred and as long as the property owner's land could qualify for placement in an agricultural district pursuant to section 929.02 of the Revised Code. The board shall regularly review the use and ownership of the property for which the collection of assessments has been deferred pursuant to this division, and upon finding that the land could no longer qualify for placement in an agricultural district pursuant to section 929.02 of the Revised Code, the board shall immediately collect, without interest, the full amount of the assessment deferred. (C) The board of county commissioners shall send a notice by regular or certified mail to all owners of property on which assessments have been deferred pursuant to division (A) of this section, which lists the expiration of the deferment, not later than two hundred ten days prior to the expiration of the deferment of those assessments. (D) The board shall collect assessments, without interest, which have been deferred pursuant to division (A) of this section upon expiration of the maximum time for which deferments were made; provided that for a property owner who requests in writing, no later than six months prior to the expiration of the deferment period, that payment of the deferred assessments be in installments, the board of county commissioners upon expiration of the deferment period may by resolution further certify for collection pursuant to section 6117.33 of the Revised Code, such deferred assessments in installments over not more than twenty years, as determined by the board, together with interest thereon each year on the unpaid balance at the same rate borne by bonds of the county which shall be issued in anticipation thereof as provided in Chapter 133. of the Revised Code. Prior to the expiration of the maximum time of deferment, the board shall regularly review the use of the property for which the collection of assessments has been deferred and upon finding that the use of the land has changed from the use at the time of the deferment so that the benefit of the improvement can then be realized, the board shall immediately collect the full amount of the assessment for the portion of the property for which the use has so changed, without interest.
|
Section 6117.07 | Determination to proceed with construction.
Effective:
September 29, 2011
Latest Legislation:
House Bill 153 - 129th General Assembly
After the expiration of the period of five days provided for in section 6117.06 of the Revised Code for the filing of written objections, the board of county commissioners shall determine whether or not it will proceed with the construction of the improvement mentioned in such section. Notice of the time and place of each meeting of the board of county commissioners, at which the resolution to proceed with the construction of such improvement will be considered, shall be given in writing to all persons who filed written objections as provided in section 6117.06 of the Revised Code. Such notice shall contain the following language in addition to the time and place of the meeting of the board: "any person, firm, or corporation desiring to appeal from the final order or judgment of the board upon any of the questions mentioned in section 6117.09 of the Revised Code shall, on or before the date of the passage of the improvement resolution, give notice in writing of an intention to appeal, specifying therein the matters to be appealed from." If it decides to proceed therewith, the board shall ratify or amend the plans for the improvement and the character and termini thereof, the boundaries of the assessment district, and the tentative assessment, and may cause such revision of plans, boundaries, or assessments as the board considers necessary to be made by the county sanitary engineer. If the boundaries of the assessment district are amended so as to include any property not included within the boundaries as established by the resolution of necessity provided for in section 6117.06 of the Revised Code, the owners of all such property shall be notified by mail if their addresses are known, and notice shall be published once a week for two consecutive weeks in a newspaper of general circulation within the county or as provided in section 7.16 of the Revised Code that such amendments have been adopted and that a hearing will be given by the board at a time and place stated in such notice, at which all persons interested will be heard by the board. The date of such hearing shall be not less than twenty-four days after the first publication of such notice, and the hearing shall be conducted and records kept in the same manner as the first hearing. Five days shall be allowed for the filing of written objections as provided in such section for the first hearing. After the expiration of such fiveday period, the board shall ratify the plans for the improvement and the character and termini thereof, the boundaries of the assessment district, and the tentative assessment, or shall further amend the same. If the boundaries of the assessment district are amended so as to include any property not included in the assessment district as originally established or previously amended, further notice and hearing shall be given to the owners of such property in the same manner as for the first amendment of such boundaries, and the same procedure shall be repeated until all property owners affected have been given an opportunity to be heard. If the owners of all property added to an assessment district by amendment of the original boundaries thereof waive objection to such amendment in writing, no further notice or hearing shall be given. After the board has ratified the plans for the improvement and the character and termini thereof, the boundaries of the assessment district, and the tentative assessment, either as originally presented or as amended, and if it decides to proceed therewith, the board shall adopt a resolution to be known as the improvement resolution. Said improvement resolution shall declare the determination of such board to proceed with the construction of the improvement provided for in the resolution of necessity, in accordance with the plans and specifications provided for such improvement as ratified or amended, and whether bonds or certificates of indebtedness shall be issued in anticipation of the collection of special assessments, as provided in section 6117.08 to 6117.45, inclusive, of the Revised Code, or that money in the county treasury unappropriated for any other purpose shall be appropriated to pay for said improvement.
|
Section 6117.08 | Proceed to issue or incur public obligations and construct the improvement.
Effective:
March 12, 2001
Latest Legislation:
House Bill 549 - 123rd General Assembly
After the adoption of a resolution to proceed with an improvement as provided for in section 6117.07 of the Revised Code, the construction of the improvement shall be deferred until ten days have elapsed. If, at the expiration of that period, no appeal has been effected by any property owner as provided in sections 6117.09 to 6117.24 of the Revised Code, the action of the board of county commissioners shall be final, and the board may proceed to issue or incur public obligations and construct the improvement. If, at the end of that ten days, any owner of property to be assessed for the improvement has effected an appeal, the construction of the improvement shall be deferred until the matters appealed from have been disposed of in court.
|
Section 6117.09 | Appeal to probate court.
Effective:
October 22, 1972
Latest Legislation:
Senate Bill 397 - 109th General Assembly
Any owner of property to be assessed or taxed for an improvement under sections 6117.01 to 6117.45 or sections 6103.01 to 6103.30 of the Revised Code, may appeal to the probate court from the action of the board of county commissioners in determining to proceed with the improvement in regard to any of the following matters: (A) The necessity of the improvement, including the question whether the cost of the improvement will exceed the benefits resulting therefrom; (B) Boundaries of the assessment district; (C) The tentative apportionment of the assessment. Such appeal shall be effected within ten days after the passage of the resolution to proceed with the improvement. No appeal shall be allowed from said decision of the board except as to the tentative apportionment of the assessment if the owners of land tentatively assessed for at least eighty-five per cent of the cost of said improvement under sections 6117.01 to 6117.45, or sections 6103.01 to 6103.30 of the Revised Code, have consented in writing to the action of the board in determining to proceed with said improvement. If such an appeal to the probate court has been perfected by any property owner prior to procuring such consent in writing of the owners of land tentatively assessed for at least eighty-five per cent of the cost of said improvement, the probate court before whom such appeal is pending, on the motion of the board or any owner of land assessed for said improvements, shall dismiss so much of said appeal as refers to the necessity of the improvement or the boundaries of said district upon the introduction of satisfactory proof of such written consent of the owners of land tentatively assessed for at least eighty-five per cent of the cost of the improvement as provided for in this section. Such property owner may also appeal from the decision of the board in refusing to grant the prayer of any petition for improvements under sections 6117.01 to 6117.40 of the Revised Code. If the director of environmental protection has made an order declaring that any improvement is necessary for the public health and welfare as provided in section 6117.34 or 6103.17 of the Revised Code, no property owner shall have the right to appeal from the action of the board declaring such improvement necessary.
|
Section 6117.10 | Appeal when improvement is located in two or more counties.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
Any person, firm, or corporation desiring to appeal to the probate court as provided in section 6117.09 of the Revised Code, when the improvement is located in two or more counties, may appeal to the probate court of the county in which property of such appellant to be assessed for such improvement is located. Any person, firm, or corporation desiring to appeal from the final order or judgment of the board upon any of the questions mentioned in such section, shall on or before the date of the passage of the improvement resolution give notice in writing of an intention to appeal, specifying therein the matters to be appealed from. The board shall fix the amount of the bond to be given by the appellant, which amount shall be reasonable, and shall make an entry thereof upon its journal. The appellant within ten days thereafter shall file with the county auditor a bond in the amount so fixed with sureties to be approved by the auditor, and such bond shall be conditioned to pay all costs made on the appeal if the appellant fails to sustain such appeal or the same is dismissed.
|
Section 6117.11 | Appeal when petition for improvement is dismissed.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
In case the petition for an improvement is dismissed, or the prayer thereof is not granted, then a person, firm, or corporation desiring to appeal therefrom must give the notice provided for in section 6117.10 of the Revised Code, on the date when the order is made dismissing said petition, or refusing to grant the prayer thereof, and file the bond required within the time prescribed in such section.
|
Section 6117.12 | Appeal by guardian of minors or other persons under disability.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
The guardian of minors or other persons under disability may appeal to the probate court as provided in sections 6117.09 to 6117.11, inclusive, of the Revised Code, without giving bond for the payments of costs. The taking of such appeal must first be authorized by the court which appointed such guardian. The probate court shall make an entry showing such disability on the journal. The estates of such persons shall be liable for all costs adjudged against them or their legal representatives.
|
Section 6117.13 | Transmission of original papers in proceedings and certified transcript of record.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
Within ten days after the filing of an appeal bond provided for in section 6117.10 or 6117.11 of the Revised Code, or the making of the entry provided for in section 6117.12 of the Revised Code, the board of county commissioners shall transmit to the probate court the original papers in the proceedings, and a certified transcript of the record of said board of all proceedings in connection therewith. Upon receipt thereof, the probate judge shall forthwith docket the cause, and the appellants shall be designated as the plaintiffs, and the board shall be designated as the defendant.
|
Section 6117.14 | Hearing on appeal.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
The probate judge shall designate a day not exceeding five days after the docketing of the cause as provided in section 6117.13 of the Revised Code for the hearing of all preliminary questions and motions on the appeal, and for the examination of the papers and proceedings. On the day so fixed, all preliminary motions and questions arising upon the appeal shall be heard and determined, and if the probate court finds that the proceedings are irregular, or that the appeal is not perfected according to law, it shall dismiss such appeal at the cost of the appellants, and certify such dismissal with its proceedings thereon to the board of county commissioners. The court may waive technical defects, errors, or omissions in such proceedings.
|
Section 6117.15 | Trial in probate court.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
If the probate judge finds that an appeal under sections 6117.09 to 6117.24, inclusive, of the Revised Code, has been properly perfected, and that the proceedings are substantially regular, he shall fix a day not more than twenty days thereafter for the trial of the case, and shall publish at least twice in a newspaper of general circulation within the county a notice that such appeal has been made and stating the time and place of such trial. The first publication shall be at least fifteen days before such trial, and the second publication shall be at least eight days before such trial. At the time so fixed the parties shall offer their evidence to the court upon the matters appealed from. The rules of law and procedure governing civil cases in the court of common pleas shall apply to the trial of the cause in the probate court.
|
Section 6117.16 | Action when more than one party appeals.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
If more than one party appeals in regard to the same improvement, the probate court shall order the cases to be consolidated and tried together, but the rights of each person, firm, or corporation as to the inclusion of their property in the assessment district or as to the apportionment of the tentative assessment shall be separately determined by the court in its verdict.
|
Section 6117.17 | Court findings.
Effective:
March 17, 1987
Latest Legislation:
House Bill 412 - 116th General Assembly
At the conclusion of the trial provided for in section 6117.15 of the Revised Code, the probate court shall find separately upon each claim for adjustment of the apportionment of the tentative assessment, if the appeal is from the judgment of the board of county commissioners in reference to apportionment of such assessment. The court shall determine whether the improvement petitioned for or granted will be necessary for the public health, convenience, or welfare, or whether the cost of it will exceed the benefit resulting from such improvement, or whether the boundaries of the assessment district should be modified, if the appeal is from an order establishing the proposed improvement or dismissing or refusing to grant the prayer of the petition or establishing the boundaries of the assessment district. If the court finds that the cost of the improvement will exceed the benefit resulting from it, it shall declare that the improvement is not necessary for the public health, convenience, or welfare. No property shall be added to the assessment district until the owners of it have been given an opportunity to be heard by the court. A notice of such hearing shall be served on such property owners by the court in the manner provided for the service of summons in civil actions. If such owners are not residents of the county, or if in any case it appears by the return of the notice that such owner cannot be found, the notice shall be published at least twice in a newspaper of general circulation within the county, and the date of such hearing shall be at least one week after service of notice or of the second publication of such notice. If a new trial is not granted for cause shown, the court shall render a judgment ordering such modification of the tentative assessment, or of the boundaries of the assessment district as the court determines. The court shall also make a finding for or against the improvement.
|
Section 6117.18 | Record - costs.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
The probate judge shall make a record of all proceedings before him, and tax the cost in favor of the prevailing party and against the losing party. If more than one matter is appealed from, and a party prevails as to one matter and loses as to another, the probate court shall determine how much of the costs each party shall pay. The costs on motions or continuance and the like shall be taxed and paid as the court directs. If there are several persons upon the side taxed with costs the court shall apportion the costs equitably among them, and in case several persons are interested on one side of the case and part of them fail, the court shall make such order as to costs as it deems equitable. In cases not specifically provided for, the court shall render such judgment in respect to costs as is equitable. The board of county commissioners shall pay any costs adjudged against it out of the county treasury.
|
Section 6117.19 | Appeal made in reference to necessity of improvement.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
If an appeal has been made in reference to the necessity of the improvement as provided in section 6117.09 of the Revised Code, and it appears from the transcript certified to the board of county commissioners by the probate judge that the proposed improvement is not necessary for the public health, convenience, and welfare, or that the cost thereof will exceed the benefits resulting from such improvement, the board shall abandon the improvement. If it appears from such transcript that the improvement is necessary for the public health, convenience, and welfare and that the cost thereof will not exceed the benefits resulting therefrom, the board may proceed with the improvement.
|
Section 6117.20 | Appeal made in reference to boundaries of assessment district or to tentative assessment.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
If an appeal has been made in reference to the boundaries of the assessment district or to the tentative assessment as provided in section 6117.09 of the Revised Code, and it appears from the transcript certified to the board of county commissioners by the probate judge that the boundaries of the assessment district should be changed or that the tentative assessment should be modified, the board may make such changes or modifications and proceed with the improvement, provided that the necessity of such improvement has not been denied by the probate court or the cost thereof found to exceed the benefits resulting from such improvement.
|
Section 6117.21 | Judgment establishing improvement.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
If an appeal is taken from the order of the board of county commissioners dismissing or refusing to grant the prayer of the petition, and the probate court finds in favor of the improvement, it shall render judgment establishing such improvement, unless it grants a new trial, and the improvement shall henceforth be established unless the judgment of said court is reversed on appeal.
|
Section 6117.22 | Fees and compensation of officers.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
For their services required on appeal the officers and other persons mentioned in sections 6117.01 to 6117.40, inclusive, of the Revised Code, are entitled to the fees and compensation which they are entitled to by law for like services in other cases.
|
Section 6117.23 | Appeal from probate court.
Effective:
March 12, 2001
Latest Legislation:
House Bill 549 - 123rd General Assembly
The final judgment of the probate court may be reviewed on appeal as in other cases. If an appeal is prosecuted from the judgment of the probate court as to the necessity of the improvement, the construction of the improvement shall be deferred until the appeal is finally disposed of. If an appeal is prosecuted from the judgment of the court as to the inclusion of any property in the assessment district or as to the apportionment of the tentative assessment, the board of county commissioners may proceed with the construction of the improvement in accordance with the transcript of the probate court and thereafter shall adjust those matters to the extent necessary in accordance with their final adjudication.
|
Section 6117.24 | Manifest error in proceedings.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
Any court in which an action is brought to enjoin, reverse, or declare void the proceedings by which any improvement has been made or ordered to be made under sections 6117.01 to 6117.45, inclusive, or 6103.02 to 6103.30, inclusive, of the Revised Code, or to enjoin a collection of a tax or assessment levied for such purpose, or any part thereof, or to which appeal is taken under section 6117.09 of the Revised Code to declare the improvement unnecessary or to amend the boundaries of any assessment district, or to modify the tentative assessment prior to the construction of any improvement, if there is manifest error in such proceedings affecting the right of the plaintiff in such action, may set such proceedings aside as to him without affecting the rights or liabilities of the other parties in interest. The court shall allow parol testimony that said improvement will be conducive to the public health, convenience, and welfare and that any steps required by law for an improvement have been substantially complied with, notwithstanding any errors or defects in any record required to be kept by any board or officer, and without finding error the court may correct any gross injustice in the assessment made by the board of county commissioners. The court on the final hearing shall make such order as it deems equitable, and order any tax or assessment levied against the plaintiff to remain on the duplicate for collection, or order it to be levied in whole or in part, or perpetually enjoin it or any part thereof, or if it has been paid under protest, order the whole or such part thereof as it deems proper to be refunded. The cost of such action shall be apportioned among the parties or paid out of the county treasury as the court directs.
|
Section 6117.25 | Payment for costs of improvement.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
(A) The board of county commissioners may pay the whole or any part of the cost of constructing, maintaining, repairing, or operating any improvement provided for in this chapter, including the payment of a county sanitary engineer and the sanitary engineer's assistants and other necessary expenses. Insofar as such expenses relate to the construction of a permanent improvement, they may be considered as part of the cost of such improvement and bonds may be issued therefor. (B) Bonds and notes in anticipation thereof, including bonds issued in anticipation of the collection of assessments deferred pursuant to sections 6117.061 and 6117.33 of the Revised Code, may be issued by the board pursuant to Chapter 133. of the Revised Code, to finance any such improvement, provided that where a separate issue of bonds is issued in anticipation of the collection of deferred assessments, the first principal maturity of such bonds may be not later than five years from the date of such bonds. Bonds issued in anticipation of the collection of assessments deferred pursuant to sections 6117.061 and 6117.33 of the Revised Code and notes issued in anticipation of such bonds shall be considered for all purposes under this chapter and Chapter 133. of the Revised Code as being bonds or notes issued in anticipation of the levy or collection of special assessments. (C) Bonds may be issued by the board under Chapter 165. of the Revised Code to finance such improvements payable solely from revenues generated by the improvements.
|
Section 6117.251 | Sanitary or drainage facility improvements.
Effective:
September 29, 2011
Latest Legislation:
House Bill 153 - 129th General Assembly
(A) After the establishment of any county sewer district, the board of county commissioners may determine by resolution that it is necessary to provide sanitary or drainage facility improvements or prevention or replacement facility improvements and to maintain and operate the improvements within the district or a designated portion of the district, that the improvements, which shall be generally described in the resolution, shall be constructed, that funds are required to pay the preliminary costs of the improvements to be incurred prior to the commencement of the proceedings for their construction, and that those funds shall be provided in accordance with this section. (B) Prior to the adoption of the resolution, the board shall give notice of its pendency and of the proposed determination of the necessity of the improvements generally described in the resolution. The notice shall set forth a description of the properties to be benefited by the improvements and the time and place of a hearing of objections to and endorsements of the improvements. The notice shall be given by publication in a newspaper of general circulation in the county once a week for two consecutive weeks, by publication as provided in section 7.16 of the Revised Code, by mailing a copy of the notice by first class or certified mail to the owners of the properties proposed to be assessed at their respective tax mailing addresses, or by a combination of these manners, the first publication to be made or the mailing to occur at least two weeks prior to the date set for the hearing. At the hearing, or at any adjournment of the hearing, of which no further published or mailed notice need be given, the board shall hear all persons whose properties are proposed to be assessed and the evidence it considers to be necessary. The board then shall determine the necessity of the proposed improvements and whether the improvements shall be made by the board and, if they are to be made, shall direct the preparation of tentative assessments upon the benefited properties and by whom they shall be prepared. (C) In order to obtain funds for the preparation of a general or revised general plan of sewerage or drainage for the district or part of the district, for the preparation of the detailed plans, specifications, estimate of cost, and tentative assessment for the proposed improvements, and for the cost of financing and legal services incident to the preparation of all of those plans and a plan of financing the proposed improvements, the board may levy upon the properties to be benefited in the district a preliminary assessment apportioned according to benefits or to tax valuation or partly by one method and partly by the other method as the board may determine. The assessments shall be in the amount determined to be necessary to obtain funds for the general and detailed plans and the cost of financing and legal services and shall be payable in the number of years that the board shall determine, not to exceed twenty years, together with interest on any public obligations that may be issued or incurred in anticipation of the collection of the assessments. (D) The board shall have power at any time to levy additional assessments according to benefits or to tax valuation or partly by one method and partly by the other method as the board may determine for the purposes described in division (C) of this section upon the benefited properties to complete the payment of the costs described in division (C) of this section or to pay the cost of any additional plans, specifications, estimate of cost, or tentative assessment and the cost of financing and legal services incident to the preparation of those plans and the plan of financing, which additional assessments shall be payable in the number of years that the board shall determine, not to exceed twenty years, together with interest on any public obligations that may be issued or incurred in anticipation of the collection of the additional assessments. (E) Prior to the adoption of a resolution levying assessments under this section, the board shall give notice either by one publication in a newspaper of general circulation in the county, or by mailing a copy of the notice by first class or certified mail to the owners of the properties proposed to be assessed at their respective tax mailing addresses, or by both manners, the publication to be made or the mailing to occur at least ten days prior to the date of the meeting at which the resolution shall be taken up for consideration; that notice shall state the time and place of the meeting at which the resolution is to be considered. At the time and place of the meeting, or at any adjournment of the meeting, of which no further published or mailed notice need be given, the board shall hear all persons whose properties are proposed to be assessed, shall correct any errors and make any revisions that appear to be necessary or just, and then may adopt a resolution levying upon the properties determined to be benefited the assessments as so corrected and revised. The assessments levied by the resolution shall be certified to the county auditor for collection in the same manner as taxes in the year or years in which they are payable. (F) Upon the adoption of the resolution described in division (E) of this section, no further action shall be taken or work done until ten days have elapsed. If, at the expiration of that period, no appeal has been effected by any property owner as provided in this division, the action of the board shall be final. If, at the end of that ten days, any owner of property to be assessed for the improvements has effected an appeal, no further action shall be taken and no work done in connection with the improvements under the resolution until the matters appealed from have been disposed of in court. Any owner of property to be assessed may appeal as provided and upon the grounds stated in sections 6117.09 to 6117.24 of the Revised Code. If no appeal has been perfected or if on appeal the resolution of the board is sustained, the board may authorize and enter into contracts to carry out the purposes for which the assessments have been levied without the prior issuance of notes, provided that the payments under those contracts do not fall due prior to the time by which the assessments are to be collected. The board may issue and sell bonds with a maximum maturity of twenty years in anticipation of the collection of the assessments and may issue notes in anticipation of the issuance of the bonds, which notes and bonds, as public obligations, shall be issued and sold as provided in Chapter 133. of the Revised Code.
|
Section 6117.27 | Contracts for construction of improvements.
Effective:
December 9, 1967
Latest Legislation:
House Bill 428 - 107th General Assembly
After the issuance and sale of bonds or certificates of indebtedness, as provided in sections 6117.01 to 6117.45, inclusive, of the Revised Code, the board of county commissioners shall enter into a written contract in accordance with sections 307.86 to 307.92, inclusive, of the Revised Code. The contract shall be between the board and the bidder, and the board shall pay the contract price in cash. Such payment may be made in proper installments as the work progresses. When there is reason to believe that there is collusion or combination among the bidders, the bids of those concerned therein shall be rejected. Whenever it becomes necessary, in the opinion of such board, in the prosecution of any such work or improvements, to make alterations or modifications in such contract, such alterations or modifications shall only be made by such board by resolution. Such resolution shall be of no effect until the prices to be paid for work or material, or both, caused by such alterations or modifications, have been agreed upon in writing and signed by the contractor and said board. No contractor for any such work shall recover anything for additional work or materials required by any alterations or modifications or for any other cause due to such alterations or modifications, unless such contract is made as provided in this section, nor shall he in any event recover for such work or materials or other cause more than the agreed price. The money derived from the lawfully authorized bonds or certificates of indebtedness sold as provided in section 6117.25 of the Revised Code, shall not thereafter be considered unappropriated until the county is fully discharged from such contract.
|
Section 6117.28 | Petition by landowners for improvements.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
Whenever the owners of all the lots and lands to be assessed for any sanitary or drainage facility improvement or any prevention or replacement facility improvement provided for in this chapter, by petition in writing, request the board of county commissioners to provide for the acquisition or construction, maintenance, and operation of the improvement, describing the improvement and the lots and lands owned by them respectively to be assessed to pay the cost of acquisition or construction, maintenance, and operation of the improvement and consenting that their lots and lands may be assessed to pay the cost of the acquisition or construction of the improvement and of its maintenance and operation as provided in this chapter, and waive all legal notices otherwise required, the board may have the county sanitary engineer prepare, or otherwise cause to be prepared, the necessary plans, specifications, and estimate of cost of the acquisition or construction, maintenance, and operation of the improvement and a tentative assessment. When the owners state, in writing, that they have examined the estimate of cost and tentative assessment, that they have no objections to them, and that, in case bonds are proposed to be issued prior to the acquisition or construction of the improvement, they waive their right or option to pay the assessments in cash, the board may proceed as provided in this chapter to cause the improvement to be acquired or constructed and to cause provision to be made for the payment of the cost of its acquisition or construction, maintenance, and operation, except that none of the notices otherwise required by law need be given and no opportunity need be provided for the filing of objections to the improvement, its character and termini, the boundaries of the assessment district, or the tentative assessment or, if bonds are issued prior to the acquisition or construction of the improvement, for paying the assessments in cash. The board may proceed to issue or incur public obligations in the required amount, complete the acquisition or construction of the improvement, and levy and collect the assessments authorized by this chapter. No person or public agency shall have the right to appeal from any decision or action of the board in the matter except refusal by the board to proceed with the improvement. The tentative assessment provided for in this section shall be for the information of property owners and shall not be levied or certified to the county auditor for collection. On completion of the improvement, its cost shall be determined, and the county sanitary engineer shall prepare, or otherwise cause to be prepared, a revised assessment based on the actual cost and in substantially the same proportion as the tentative assessment. The board shall confirm and levy the revised assessment and certify it to the county auditor for collection.
|
Section 6117.29 | Cost of improvement to include engineering, necessary publications, inspection, interest on public obligations.
Effective:
March 12, 2001
Latest Legislation:
House Bill 549 - 123rd General Assembly
The cost of any improvement provided for in this chapter and the cost of its maintenance and operation shall include, in addition to the cost of its acquisition or construction, the cost of engineering, necessary publications, inspection, interest on public obligations, and all other items of cost incident to the improvement as described in division (B) of section 133.15 of the Revised Code. The county may pay from available county funds any part of the cost of the improvement and any part of the cost of its maintenance and operation if the board of county commissioners considers the payment to be just.
|
Section 6117.30 | Assessment district assessments.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
The cost of the acquisition or construction of sanitary or drainage facilities or prevention or replacement facilities to be paid by assessments shall be assessed, as an assessment district assessment, upon all the property within the county sewer district found to be benefited in accordance with the special benefits conferred, less any part of the cost that is paid by the county at large from other available funds. State land so benefited shall bear its portion of the assessed cost.
|
Section 6117.31 | Actual costs - collection.
Latest Legislation:
Senate Bill 466 - 108th General Assembly
Upon the completion of any improvement under sections 6117.01 to 6117.45, inclusive, of the Revised Code, the actual cost thereof shall be ascertained and to such actual cost shall be added an amount equal to the interest accrued and to accrue before the first installment of such assessment is collected upon certificates of indebtedness and upon bonds authorized by such sections or upon the contribution of the county to be paid from the assessment under an agreement pursuant to section 6121.13 of the Revised Code, between the county and the Ohio water development authority, for the construction of an improvement for which the county can levy assessments as provided in Chapter 6117. of the Revised Code, and the sum so arising, less the portion thereof to be paid by the county at large, shall be assessed against the lots and parcels of land within the assessment district found to be benefited by such improvement. For the purpose of paying the county sanitary engineer provided for in section 6117.01 of the Revised Code, and for paying his assistants and all of his other necessary expenses, and for the purpose of paying that part of the cost of the improvement to be paid by the county or of the interest to accrue thereon, the board of county commissioners may levy taxes in addition to all other taxes authorized by law. Such levy shall be subject to all the limitations provided by law upon the aggregate amount, rate, maximum rate, and combined maximum rate of taxation.
|
Section 6117.311 | Levying tax and issuing bonds to pay costs of improvement.
Effective:
March 23, 1981
Latest Legislation:
House Bill 1062 - 113th General Assembly
For the purpose of paying for a part or all of the cost of any improvement under this chapter in a sewer district created under the provisions of section 6117.01 of the Revised Code, or in a designated subdistrict thereof, the board of county commissioners may levy a tax under Chapter 5705. of the Revised Code upon all of the property listed and assessed for taxation in such sewer district or subdistrict and may authorize, issue, and execute bonds under the provisions of Chapter 133. of the Revised Code for and on behalf of said sewer district or subdistrict as an indebtedness of said district or subdistrict payable from taxes which the board of county commissioners shall levy upon all of the property listed and assessed for taxation therein. Bonds shall be authorized and issued only after approval by a vote of the electors of such sewer district or subdistrict and the total net indebtedness created or incurred and outstanding under this section shall not exceed five per cent of the tax duplicate valuation of the district or subdistrict. The board of county commissioners shall pass its resolution declaring the necessity for the improvement and the submission of the question of whether to levy a tax or the question of whether to issue bonds to the electors of the sewer district or subdistrict by unanimous vote of all its members, and shall cause to be filed with the county auditor and the board of elections of the county an accurate map or plat showing the boundaries of any such sewer district or subdistrict at least seventy-five days prior to the passage of such resolution. If the entire cost of the improvement is to be paid from the proceeds of a bond issue under the provisions of this section and Chapter 133. of the Revised Code, the board of county commissioners need not provide for a public hearing or take any proceedings under the provisions of section 6117.06 or 6117.07 of the Revised Code. Bonds issued under this section shall not be considered within the debt limitations of the county prescribed by section 133.05 of the Revised Code. For the purposes of this section, such sewer district or subdistrict is constituted a "subdivision" and "taxing unit"; the board of county commissioners is the "taxing authority" and "bond authorizing authority" thereof; and the county auditor is the "fiscal officer" thereof, within the purview of Chapters 133. and 5705. of the Revised Code. No power granted in this section nor the exercise thereof shall be construed as limiting the authority or jurisdiction of the board of county commissioners or of any other political subdivision to take any action in a sewer district or subdistrict under any other sections of the Revised Code.
|
Section 6117.32 | Revised assessment.
Effective:
March 12, 2001
Latest Legislation:
House Bill 549 - 123rd General Assembly
The county sanitary engineer, upon the completion of any improvement in accordance with this chapter, shall prepare, or otherwise cause to be prepared, and shall present to the board of county commissioners a revised assessment based on the tentative assessment previously ratified by the board for the improvement or, if the tentative assessment has been revised by order of court, based on the revised tentative assessment, the assessment levied on each piece of property being modified in substantially the same proportion as the actual cost of the improvement, including incidental costs, bears to the estimated cost on which the tentative assessment was based. No notice of the revised assessment shall be given unless the actual cost exceeds the estimated cost. If the actual cost exceeds the estimated cost, notice shall be given to all property owners within the assessment district and shall be published as provided by section 6117.07 of the Revised Code for amendments of the tentative assessment, and any property owner may appeal as provided for in the case of a tentative assessment. The board shall confirm the revised assessment, and, when so confirmed, it shall be final and conclusive. If an appeal has been made, that confirmation shall be subject to the finding of the court. The board, at intervals it considers expedient, may levy an additional assessment on the lots and parcels of land assessed for the improvement, including state land, in order to pay the cost of the maintenance, repair, and operation of the improvement after its completion. No further notice of that additional assessment shall be necessary unless the amount of it exceeds ten per cent of the original cost of acquiring or constructing the improvement. If that additional assessment exceeds ten per cent of the original cost of acquiring or constructing the improvement, the method and manner of making that additional assessment, together with the notice of it, shall be the same as provided in this chapter for the original assessment. That additional assessment shall be subject to any applicable provisions of section 6117.33 of the Revised Code, provided that the assessment may bear interest at a rate as the board determines to be appropriate.
|
Section 6117.33 | Annual certification of assessments.
Effective:
September 21, 1982
Latest Legislation:
House Bill 379 - 114th General Assembly
On or before the second Monday in September, annually, the board of county commissioners shall certify all of the assessments provided for in section 6117.32 of the Revised Code to the county auditor, including all assessments deferred pursuant to section 6117.061 of the Revised Code, stating the amount and the time of payment thereof, and in accordance therewith the auditor shall record the same in a book to be known as the "sewer improvement record" of said county, showing separately the assessments to be collected forthwith and the assessments whose collection has been deferred by the board pursuant to section 6117.061 of the Revised Code. Such assessment, including the assessments deferred by the board pursuant to section 6117.061 of the Revised Code, shall bear interest at the rate that the bonds authorized by section 6117.25 of the Revised Code bears, or at the rate that the contribution of the county to be paid from the assessment under an agreement pursuant to section 6121.13 of the Revised Code, between the county and the Ohio water development authority, bears, and shall be a lien upon the lots and lands so assessed from the date of such record until such assessments are paid, and shall be collected in annual or semiannual installments within a period of not more than forty years, provided that interest on deferred assessments shall terminate when all of the bonds issued by the board in anticipation of such deferred assessments have been paid in full. If any such assessment is twenty-five dollars or less, or whenever the unpaid balance of any such assessment is twenty-five dollars or less, the same shall be paid in full and not in installments at the time the first or next installment would otherwise become payable. The several installments of such assessments which have not been deferred for collection pursuant to section 6117.061 of the Revised Code and interest on deferred assessments shall be placed upon the tax duplicate of the county for collection as they become due commencing with the first duplicate prepared after the assessments have been so certified, and shall be collected the same as other taxes, and shall be subject to the same penalties and interest. In case bonds have not been sold or an agreement between the county and the Ohio water development authority has not been entered into to pay the cost of the improvement the amount assessed against any lot or parcel of land may be paid within thirty days from the confirmation of the revised assessment. The board shall, annually, during the month of August, review all assessments which have been deferred for collection pursuant to section 6117.061 of the Revised Code as shown upon the auditor's "sewer improvement record" and shall determine whether, in view of changed circumstances concerning the property since the date of the original deferment, it is no longer inequitable to certify such assessment or any portion thereof to the county auditor for collection. On or before the second Monday in September, annually, the board shall direct the county auditor to place on the tax duplicate for collection such deferred assessments or portions thereof as the board determines should no longer be deferred, or which the property owner has requested to be collected, and thereupon the county auditor shall place the same upon the first duplicate prepared by him thereafter and shall collect the same as other taxes in such number of annual or semiannual installments within a period ending not later than the thirty-ninth year after the year in which the nondeferred assessments for such improvement were first collected, as directed by the board, provided that the number of installments shall not be less than that required to coincide with the remaining principal payments on the bonds issued in anticipation of the collection of such assessments and in no event shall the payment period be less than five years. On or before the second Monday of September of the twentieth year following the adoption of the resolution confirming the revised assessment, the board shall direct the county auditor to place on the tax duplicate for collection all deferred assessments or parts thereof confirmed by such resolution which the board has not theretofore directed the auditor to collect, and thereupon the auditor shall place the same upon the first tax duplicate prepared by him thereafter and shall collect the same as other taxes in such number of annual or semiannual installments within a period of not more than twenty and not less than five years as directed by the board, provided that the final installment shall not be made payable earlier than the payment date of the final installment of the nondeferred assessments for such improvement. All assessments when collected, together with all interest thereon, shall be applied respectively to the purposes for which such assessments have been made and to no other purpose, provided that any installments of deferred assessments collected by the treasurer subsequent to the retirement of the bonds issued in anticipation of the collection of such deferred assessments, shall be allocated by him to the several county funds, including the special fund provided for by section 6117.02 of the Revised Code, in proportion to their respective contributions to the retirement and discharge of such bonds.
|
Section 6117.34 | Complaint of unsanitary conditions.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
Whenever the legislative authority or board of health, or the officers performing the duties of the legislative authority or board of health, of a municipal corporation, the board of health of a general health district, or a board of township trustees makes complaint, in writing, to the environmental protection agency that unsanitary conditions exist in any county, the agency's director forthwith shall inquire into and investigate the conditions complained of. If, upon investigation of the complaint, the director finds that it is necessary for the public health and welfare that sanitary or drainage facilities or prevention or replacement facilities be acquired or constructed, maintained, and operated to serve any territory outside municipal corporations in any county, the director shall notify the board of county commissioners of the county of that finding and order that corrective action be taken. The board shall obey the order and proceed as provided in this chapter to establish a county sewer district, if required, to provide the necessary funds, to acquire or construct the facilities, and to maintain and operate the facilities, as required by the order and in a manner that is satisfactory to the director. Any part or all of the cost of the facilities or of the maintenance and operation of the facilities may be assessed upon the benefited properties as provided in this chapter.
|
Section 6117.36 | Writ of mandamus.
Effective:
October 23, 1972
Latest Legislation:
Senate Bill 394 - 109th General Assembly
If the board of county commissioners fails after thirty days after the notice and order given to it by the director of environmental protection to perform any act required of it by sections 6117.01 to 6117.40 of the Revised Code, and by any such order and notice of the director, such order may be enforced by a writ of mandamus issued by any court authorized to issue such writs.
|
Section 6117.37 | Recovery of fine, forfeiture, or penalty.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
An action may be commenced and prosecuted for the recovery of any fine, forfeiture, or penalty mentioned in sections 6117.01 to 6117.40, inclusive, of the Revised Code, from any person liable therefor, by the prosecuting attorney of the proper county in the name of the state, in the court of common pleas of such county, or such action may be commenced and prosecuted by the attorney general in such county or in Franklin county, as privided by law.
|
Section 6117.38 | Sewerage or drainage outside district.
Effective:
September 29, 2017
Latest Legislation:
House Bill 49 - 132nd General Assembly
(A)(1) After the formation of any county sewer district, the board of county commissioners may contract with a person, political subdivision, unincorporated area, or public agency located outside of the district for any of the following: (a) Depositing sewage or drainage from outside of the district in facilities acquired or constructed or to be acquired or constructed by the county to serve the district; (b) The treatment, disposal, and disposition of the sewage or drainage, on terms that the board considers equitable; (c) The provision of water supply services. (2) A person, political subdivision, unincorporated area, or public agency located outside of a county sewer district may apply to the board of county commissioners for the provision of the services specified in division (A)(1)(a), (b), or (c) of this section. (3) The amount to be paid by the person, political subdivision, unincorporated area, or public agency to reimburse the county for costs of acquiring or constructing those facilities shall not be less than the original or comparable assessment for similar property within the district or, in the absence of an original or comparable assessment, an amount that is found by the board to be reasonable and fairly reflective of that portion of the cost of those facilities attributable to the properties to be served. The board shall appropriate any moneys received for that service to and for the use and benefit of the district. The board may collect the amount to be paid by the person, political subdivision, unincorporated area, or public agency in full, in cash or in installments as a part of a connection charge to be collected in accordance with division (B) or (D) of section 6117.02 of the Revised Code, or if the properties to be served are located within the county, the same amount may be assessed against those properties, and, in that event, the manner of making the assessment, together with the notice of it, shall be as provided in this chapter. (B) Whenever sanitary or drainage facilities or prevention or replacement facilities have been acquired or constructed by, and at the expense of, a person, political subdivision, unincorporated area, or public agency and the board considers it appropriate to acquire the facilities or any part of them for the purpose of providing sewerage or drainage service to territory within a sewer district, the county sanitary engineer, at the direction of the board, shall examine the facilities. If the county sanitary engineer finds the facilities properly designed and constructed, the county sanitary engineer shall certify that fact to the board. The board may determine to purchase the facilities or any part of them at a cost that, after consultation with the county sanitary engineer, it finds to be reasonable. Subject to and in accordance with this division and division (B) or divisions (C), (D), and (E) of section 6117.06 of the Revised Code, the board may purchase the facilities or any part of them by negotiation. For the purpose of paying the cost of their acquisition, the board may issue or incur public obligations and assess the entire cost, or a lesser designated part of the cost, of their acquisition against the benefited properties in the manner provided in this chapter for the construction of original or comparable facilities. (C) As used in this section, "located outside of the district" includes an area located in a different county than the county in which the county sewer district is located.
|
Section 6117.39 | Acquisition or purchase of property.
Effective:
September 10, 2012
Latest Legislation:
House Bill 487 - 129th General Assembly
(A) Except as provided in division (B) of this section, whenever, in the opinion of the board of county commissioners, it is necessary to acquire real estate or any interest in real estate for the acquisition, construction, maintenance, or operation of any sewer, drainage, or other improvement authorized by this chapter, or to acquire the right to construct, maintain, and operate the sewer, drainage, or other improvement in and upon any property within or outside of a county sewer district, it may purchase the real estate, interest in real estate, or right by negotiation. If the board and the owner of the real estate, interest in real estate, or right are unable to agree upon its purchase and sale, or the amount of damages to be awarded for it, the board may appropriate the real estate, interest, or right in accordance with sections 163.01 to 163.22 of the Revised Code, except that the board, in the exercise of the powers granted by this section or any other section of this chapter, may not appropriate real estate or personal property owned by a municipal corporation. (B)(1) For the purposes of division (B) of this section, any of the following constitutes a public exigency: (a) A finding by the director of environmental protection that a public health nuisance caused by an occasion of unavoidable urgency and suddenness due to unsanitary conditions compels the immediate construction of sewers for the protection of the public health and welfare; (b) The issuance of an order by the board of health of a health district to mitigate or abate a public health nuisance that is caused by an occasion of unavoidable urgency and suddenness due to unsanitary conditions and compels the immediate construction of sewers for the protection of the public health and welfare; (c) With respect to an affected parcel of property, an improvement required as a result of a federally imposed or state-imposed consent decree that prohibits future sewer inflows, combined sewer overflows, or sewer back-ups. (2) If the board of county commissioners is unable to purchase property for the purpose of addressing a public exigency pursuant to division (B) of this section, the board of county commissioners may adopt a resolution finding that it is necessary for the protection of the public health and welfare to appropriate property that the board of county commissioners considers needed for that purpose. The resolution shall contain a definite, accurate, and detailed description of the property and the name and place of residence, if known or with reasonable diligence ascertainable, of the owners of the property to be appropriated. The board of county commissioners shall fix in its resolution what it considers to be the value of the property to be appropriated, which shall be the board's determination of the compensation for the property and shall be supported by an independent appraisal, together with any damages to the residue. The board shall deposit the compensation so determined, together with an amount for the damages to the residue, with the probate court or the court of common pleas of the county in which the property, or a part of it, is situated. Except as otherwise provided in this division, the power to appropriate property for the purposes of this division shall be exercised in the manner provided in sections 163.01 to 163.22 of the Revised Code for an appropriation in the time of public exigency. The board's resolution and a written copy of the independent appraisal shall accompany the petition filed under section 163.05 of the Revised Code.
|
Section 6117.40 | Sewer construction within municipal corporation.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
Whenever in the opinion of the board of county commissioners it becomes necessary to construct a sewer within the boundaries of a municipal corporation for the service of sewer districts wholly outside of such municipal corporation, the board may construct such sewer in the streets and alleys of such municipal corporation but shall restore all such streets and alleys to their original condition, and the cost thereof shall be a part of the cost of such sewer. Prior to the preparation of plans for such improvement, such municipal corporation shall be given an opportunity to co-operate in the construction and use of such sewer as provided in section 6117.03, 6117.04, or 6117.41 of the Revised Code.
|
Section 6117.41 | Contracts with other public agencies.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
At any time after the formation of any county sewer district, the board of county commissioners may enter into a contract, upon the terms and for the period of time that are mutually agreed upon, with any other public agency to prepare all necessary plans and estimates of cost and to acquire or construct any sanitary or drainage facilities or any prevention or replacement facilities that are to be used jointly by the contracting parties, and to provide for the maintenance, operation, and joint use by the contracting parties of those facilities or the maintenance, operation, and joint use of any suitable existing sanitary or drainage facilities or prevention or replacement facilities belonging to either of the contracting parties.
|
Section 6117.42 | Compensation to other public agencies providing services.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
All contracts under section 6117.41 of the Revised Code shall provide for the payment of compensation to the county or other public agency owning, acquiring, or constructing, or agreeing to acquire or construct, the sanitary or drainage facilities or prevention or replacement facilities to be jointly used in an amount agreed upon as the other party's share of the cost of acquiring or constructing the facilities. The contract also shall provide for payment of compensation to the county or other public agency owning, acquiring, or constructing the facilities and operating and maintaining them in an amount agreed upon as the other party's share of the cost of operating and maintaining them or, in lieu of all other or differing payments, and agreed price per unit of flow. A county or other public agency owning, acquiring, or constructing, or agreeing to acquire or construct, any of the facilities and agreeing to their use by another public agency shall retain full control and management of the acquisition, construction, maintenance, and operation of the facilities, unless otherwise provided in the contract and except, in the case of a county, when conveyed to a municipal corporation as provided in division (B) of section 6117.05 of the Revised Code.
|
Section 6117.43 | Payment of agreed compensation by levy of taxes or special assessments.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
A county or other public agency contracting as provided in sections 6117.41 and 6117.42 of the Revised Code for the joint use of any sanitary or drainage facilities or any prevention or replacement facilities acquired or constructed, or to be acquired or constructed, by another public agency may provide for payment of the agreed compensation by the levy of taxes or special assessments or from sanitary sewer or drainage rates and charges, if and to the extent that the public agency is authorized by the laws governing it in the acquisition, construction, maintenance, or operation of the facilities to provide for payment of the costs in respect of which the compensation is due from those sources, and may issue or incur public obligations as provided by those laws and pay the debt charges on those obligations from those sources if and to the extent so authorized.
|
Section 6117.44 | Credit of compensation.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
A county or other public agency receiving the compensation provided for in section 6117.42 of the Revised Code shall credit the amount so received to the proper fund to be used for the acquisition, construction, or operation and maintenance, as the case may be, of the sanitary or drainage facilities or the prevention or replacement facilities or for other authorized purposes.
|
Section 6117.45 | Violations - fines.
Effective:
September 23, 2008
Latest Legislation:
House Bill 562 - 127th General Assembly
No person or public agency shall tamper with or damage any sanitary or drainage facility or any prevention or replacement facility acquired or constructed by a county under this chapter or any apparatus or accessory connected with it or pertaining to it, or make any connection into or with the facility, without the permission of the board of county commissioners or in a manner or for a use other than as prescribed by the board. No person or public agency shall refuse to permit the inspection by the county sanitary engineer of any such connection. No person or public agency shall violate any other provision of this chapter. All fines collected under section 6117.99 of the Revised Code shall be paid to the county treasurer and credited to the fund that the board determines to be most appropriate after consideration of the nature and extent of the particular violations.
|
Section 6117.46 | County trunk or main sewers.
Effective:
October 23, 1972
Latest Legislation:
Senate Bill 397 - 109th General Assembly
When the director of environmental protection finds that a trunk or main sewer is necessary in a county for sanitary purposes, the board of county commissioners of such county may make surveys thereof and prepare plans and specifications thereof. Upon approval by the director of such plans and specifications, the board may construct and maintain said trunk or main sewer or part thereof within or without the limits of a municipal corporation, regulate the tapping thereof by lateral sewers, and prescribe the conditions of such tapping.
|
Section 6117.47 | Purchase or appropriation of property for county trunk or main sewers.
Effective:
October 1, 1953
Latest Legislation:
House Bill 1 - 100th General Assembly
The board of county commissioners may acquire by purchase or appropriation proceedings all real and personal property necessary for the proper construction and maintenance of a trunk or main sewer provided for in section 6117.46 of the Revised Code. The board may occupy any public road, street, avenue, or alley for such trunk or main sewer or part thereof.
|
Section 6117.48 | Eminent domain proceedings.
Effective:
January 1, 1966
Latest Legislation:
Senate Bill 94 - 106th General Assembly
When it is necessary to procure real estate or a right of way or an easement therein for a trunk or main sewer provided for in section 6117.46 of the Revised Code, and the owners thereof are unable to agree upon the compensation therefor, the board of county commissioners may appropriate it in accordance with sections 163.01 to 163.22, inclusive, of the Revised Code.
|
Section 6117.49 | Sale or disposition of county sanitary or drainage facilities.
Effective:
September 29, 2011
Latest Legislation:
House Bill 153 - 129th General Assembly
(A) If the board of county commissioners determines by resolution that the best interests of the county and those served by the sanitary or drainage facilities or the prevention or replacement facilities of a county sewer district so require, the board may sell or otherwise dispose of the facilities to another public agency or a person. The resolution declaring the necessity of that disposition shall recite the reasons for the sale or other disposition and shall establish any conditions or terms that the board may impose, including, but not limited to, a minimum sales price if a sale is proposed, a requirement for the submission by bidders of the schedule of rates and charges initially proposed to be paid for the services of the facilities, and other pertinent conditions or terms relating to the sale or other disposition. The resolution also shall designate a time and place for the hearing of objections to the sale or other disposition by the board. Notice of the adoption of the resolution and the time and place of the hearing shall be published as provided in section 7.16 of the Revised Code or once a week for two consecutive weeks, in a newspaper of general circulation in the sewer district and in the county. The public hearing on the sale or other disposition shall be held not less than twenty-four days following the date of first publication of the notice. A copy of the notice also shall be sent by first class or certified mail, on or before the date of the second publication, to any public agency within the area served by the facilities. At the public hearing, or at any adjournment of it, of which no further published or mailed notice need be given, the board shall hear all interested parties. A period of five days shall be given following the completion of the hearing for the filing of written objections by any interested persons or public agencies to the sale or other disposition, after which the board shall consider any objections and by resolution determine whether or not to proceed with the sale or other disposition. If the board determines to proceed with the sale or other disposition, it shall receive bids after advertising once a week for four consecutive weeks or as provided in section 7.16 of the Revised Code, in a newspaper of general circulation in the county and, subject to the right of the board to reject any or all bids, may make an award to a responsible bidder whose proposal is determined by the board to be in the best interests of the county and those served by the facilities. (B) A conveyance of sanitary or drainage facilities or of prevention or replacement facilities by a county to a municipal corporation in accordance with division (B) of section 6117.05 of the Revised Code may be made without regard to division (A) of this section.
|
Section 6117.51 | New public sewer construction projects.
Latest Legislation:
House Bill 411 - 125th General Assembly
If the board of health of the health district within which a new public sewer construction project is proposed or located passes a resolution stating that the reason for the project is to reduce or eliminate an existing health problem or a hazard of water pollution, the board of county commissioners of the county, by resolution, may order the owner of any premises located in a sewer district in the county, the owner's agent, lessee, or tenant, or any other occupant of the premises to connect the premises to the sewer for the purpose of discharging sewage or other waste that the board determines is originating on the premises, to make use of the connection, and to cease the discharge of the sewage or other waste into a cesspool, ditch, private sewer, privy, septic tank, semipublic disposal system as defined in division (B)(1)(a) of section 3709.085 of the Revised Code, or other outlet if the board finds that the sewer is available for use and is accessible to the premises following a determination and certification to the board by a registered professional engineer designated by it as to the availability and accessibility of the sewer. This section does not apply to any of the following: (A) Any discharge authorized by a permit issued under division (J) of section 6111.03 of the Revised Code other than a discharge to or from a semipublic disposal system as defined in division (B)(1)(a) of section 3709.085 of the Revised Code; (B) Wastes resulting from the keeping of animals; (C) Any premises that are not served by a common sewage collection system when the foundation wall of the structure from which sewage or other waste originates is more than two hundred feet from the nearest boundary of the right-of-way within which the sewer is located; (D) Any premises that are served by a common sewage collection system when both the foundation wall of the structure from which the sewage or other waste originates and the common sewage collection system are more than two hundred feet from the nearest boundary of the right-of-way within which the public sewer is located; (E) Any dwelling house located on property that is listed on the county's agricultural land tax list as being valued for tax purposes as land devoted exclusively to agricultural use under section 5713.31 of the Revised Code, when the foundation wall of the dwelling house is two hundred feet or less from the nearest boundary of the right-of-way within which the sewer is located, if both of the following also apply: (1) The sewer right-of-way for the property on which the dwelling house is located was obtained by appropriation due to a public exigency pursuant to division (B) of section 307.08, 6101.181, 6115.211, 6117.39, or 6119.11 of the Revised Code. (2) The local health department has certified that the household sewage disposal system is functioning properly. The board shall not direct an order under this section to a resident tenant unless it determines that the terms of the tenancy are such that the owner lacks sufficient rights of access to permit the owner to comply with the terms of the order. An owner, agent, lessee, tenant, or occupant shall comply with the order of the board within ninety days after the completion of service of the order upon that person as provided in this section. The board, upon written application filed prior to the expiration of the ninety-day period, may waive compliance with any order either temporarily or permanently and conditionally or unconditionally. In its resolution, the board shall direct its clerk, or the clerk's designee, to serve its order upon the owner, agent, lessee, tenant, or occupant. Service of the order shall be made personally, by leaving the order at the usual place of residence with a person of suitable age and discretion then residing therein, or by certified mail addressed to the owner, agent, lessee, tenant, or occupant at that person's last known address or to the address to which tax bills are sent. If it appears by the return of service or the return of the order forwarded by certified mail that the owner, agent, lessee, tenant, or occupant cannot be found, that person shall be served by publication of the order once in a newspaper of general circulation within the county, or if that person refuses service, that person shall be served by ordinary mail addressed to that person's last known address or to the address to which tax bills are sent. The return of the person serving the order or a certified copy of the return, or a returned receipt for the order forwarded by certified mail accepted by the addressee or anyone purporting to act for the addressee, is prima-facie evidence of the service of the order under this section. The return of the person attempting to serve the order, or the return to the sender of the order forwarded by certified mail with an indication on the return of the refusal of the addressee to accept delivery, is prima-facie evidence of the refusal of service. No owner, agent, lessee, tenant, or occupant shall violate an order issued under this section. Upon request of the board, the prosecuting attorney shall prosecute in a court of competent jurisdiction any owner, agent, lessee, tenant, or occupant who violates an order issued under this section. Each day that a violation continues after conviction for the violation of an order issued under this section and the final determination thereof is a separate offense. The court, for good cause shown, may grant a reasonable additional period of time for compliance after conviction. Any owner, agent, lessee, tenant, or occupant violating an order issued under this section also may be enjoined from continuing in violation. Upon request of the board, the prosecuting attorney shall bring an action in a court of competent jurisdiction for an injunction against the owner, agent, lessee, tenant, or occupant violating an order. The Ohio water development authority created under section 6121.02 of the Revised Code, in addition to its other powers, has the same power and shall be governed by the same procedures in a waste water facilities service area, or in any area adjacent to a public sewer operated by the authority, as a board of county commissioners in a county sewer district under this section, except that the authority shall act by order, and the attorney general, upon request of the authority, shall prosecute any person who violates an order of the authority issued under this section.
|
Section 6117.60 | Amendments to chapter are subject to 4 of HB 549 of the 123rd General Assembly.
Effective:
March 12, 2001
Latest Legislation:
House Bill 549 - 123rd General Assembly
It is the intent of the general assembly that the amendments made to this chapter by Sub. H.B. 549 of the 123rd general assembly are subject to section 4 of that act. This section does not affect the application of section 3 of that act to sections 1 and 2 of that act.
|
Section 6117.99 | Penalty.
Effective:
August 25, 1976
Latest Legislation:
Senate Bill 311 - 111th General Assembly
Whoever violates section 6117.45 or 6117.51 of the Revised Code is guilty of a minor misdemeanor.
|