Skip to main content
Back To Top Top Back To Top
This website publishes administrative rules on their effective dates, as designated by the adopting state agencies, colleges, and universities.

Rule 4906-3-02 | Preapplication meeting.

 

An applicant considering construction of a major utility facility or economically significant wind farm may request a preapplication meeting with the board staff prior to submitting an application. The results of such meeting(s) in no way constitutes approval or disapproval of a particular site or route, and in no way predetermines the board's decision regarding subsequent certification or approval.

Last updated May 30, 2024 at 9:10 AM

Supplemental Information

Authorized By: 4906.03, 4906.20
Amplifies: 4906.03, 4906.04, 4906.06, 4906.10, 4906.13, 4906.20
Five Year Review Date: 5/20/2029
Prior Effective Dates: 12/27/1976, 6/10/1989, 8/28/1998, 12/15/2003, 1/25/2009, 5/7/2009, 12/11/2015