Rule 4901:1-36-01 | Definitions.

 

(A) "Application" means an application for a transmission cost recovery rider pursuant to this chapter.

(B) "Commission" means the public utilities commission of Ohio.

(C) "Electric utility" has the meaning set forth in division (A)(11) of section 4928.01 of the Revised Code.

(D) "Staff" means the staff of the commission or its authorized representative.

Last updated June 20, 2023 at 9:15 AM

Supplemental Information

Authorized By: R.C. 4928.06
Amplifies: R.C. 4928.05, 4928.143
Five Year Review Date: 7/15/2026
Prior Effective Dates: 4/2/2009