Rule 4901:1-16-06 | Construction reports.

 

(A) Each operator shall submit reports for each important addition of its intrastate gas pipeline facilities. As used in this rule, an "important addition" means construction or alteration of a contiguous section of an operator's intrastate gas pipeline facility within a defined time frame, which involves an expenditure of either:

(1) More than five hundred thousand dollars.

(2) An amount which is more than ten per cent of the value of the operator's intrastate gas pipeline facility, provided such amount exceeds one hundred thousand dollars.

.

(B) Each operator shall submit two reports for each important addition on the form provided by the commission.

(1) The first report not later than fourteen days and not sooner than sixty days before construction work will start.

(2) The second report not later than seven days after construction work has been completed.

(C) Distribution operators shall incorporate new construction, including riser installation, as a part of their operator qualification program as described by 49 C.F.R. 192, Subpart N, as effective on the date referenced in paragraph (D) of rule 4901:1-16-02 of the Administrative Code.

Last updated June 20, 2023 at 9:23 AM

Supplemental Information

Authorized By: 4905.91
Amplifies: 4905.91, 4905.93, 4905.94
Five Year Review Date: 7/26/2026
Prior Effective Dates: 2/1/1991, 10/13/1994, 1/6/2005, 6/17/2006, 8/24/2007, 6/20/2008, 7/12/2010, 3/28/2014, 1/1/2015, 8/5/2021