Rule 1501:21-17-03 | Approval of construction by the chief.
Upon receipt of the engineer's certification as set forth in rule 1501:21-15-05 of the Administrative Code, the as-built plans and detailed final cost as set forth in rule 1501:21-15-04 of the Administrative Code, the operation, maintenance, and inspection manual as set forth in rule 1501:21-15-06 of the Administrative Code, and the emergency action plan as set forth in rule 1501:21-15-07 of the Administrative Code, the chief will within thirty days inspect the completed construction. If the chief finds that construction was completed in accordance with the approved plans, specifications, and changes, the chief will within fourteen days after inspection approve the construction and so notify the owner and the surety in writing. The approval date will be the date such notice is sent by the chief.
Last updated June 27, 2024 at 10:26 PM